The following system is to be calculated:
The following data are given:
-
Base of excavation = 65.00 m AD
-
Water level at top of system = GWT = 65.50 m AD
-
Water level at bottom of system = GWB = 67.00 m AD
|
Soil |
Base
|
Permeability
|
|
|
Sand |
63.65 |
10-4 |
19/10 |
|
Clay |
63.00 |
10-8 |
20/11 |
|
Silt |
62.00 |
10-7 |
19/10 |